GENERAL INFORMATION
Foundation date
1993 OSJC «STEELCON»,
from 2006 PCF “STEELCON”, LLCFull name
Production and construction firm “STEELCON”,
Limited liability companyAbbreviated name
PCF “STEELCON”, LLC
Legal adress
115114, Moscow, Kozhevnicheskaya st., 11/13, bld 2
TIN
7705754507
OGRN Code
5067746790678 от 25.09.2006г
Total labour force, men
600
Из них Директора
5
construction management personnel
60
technical engineering personnel
31
Steelwork assemblers
250
Electric welders
110
Drivers and crane operators
40
Crawlers and mobile cranes, pcs
23
Trucks, pcs.
15
Annual mean turnover, mln. Rub.
3.650
Mean Annual payroll budget, mln. rub.
306,00
Maximum steelwork installed volume 2013г., tn
68 970
Affilation with SRO for construction
Since 2009
Consequence class by for construction
3
up to 3 mlrd, rub.Affilation with SRO for design
Since 2010 г.
Consequence class by SRO for design
2
Up to 50 mln. rub.
Production facility floor area
Kotelniki, Dzerzhinskoe Av., 3
10.200 м2
PRODUCTION AND CONSTRUCTION FIRM
1997 - 2017
|
The company has been operating in the all-Russian market since 1993, its founders were JSC Firm “Stalkonstruktsiya” and its shareholders - the company has been faithful to its mission for 25 years. The beginning of formation of our young team became the work on installation of a 240x300 m cover shed of the Grand Sports Arena "Luzhniki" Moscow, 1996-1997, the tender on which has won JSC Firm "Stalkonstruktsiya". The unique installation, advanced load-lifting technologies of the Dutch group "Van Seumeren - Mammoet", cyclopean steel structures of the largest iron-and-steel works of the country - determined our technological and production experience, formed the main staff of the company. Another milestone project for us was the installation of a 40,000 spectator covering for the stands at the Sochi 2014 FISHT Central Olympic Stadium. From March 2011 to May 2013, the company, led by a consortium, assembled 25,000 tons of temporary and basic steel structures of the 75-meter-high dome with a span of almost 250 meters of main arches. The experience gained by our team allowed us to successfully overcome competition and to further install stadiums in Kazan, Spartak in Moscow, Yekaterinburg, Rostov-on-Don, Kaliningrad, BSA Luzhniki and VTB Arena-Dynamo. The obvious competitive advantage of the company is its own production and supply of steel structures for installation. The company's own human resources and flexible production policy allow PCF STEELCON to successfully dominate the market for large-scale construction projects.
|
FISHT Central Olympic Stadium, Sochi 2014 Supplying and installation of 25.000 t of dome steel structures, 2011-2013 |